地铁常熟路车站由市笫五建筑工程公司承建,采用独创的逆作法施工技术进行施工。工程于1992年2月10日破土动工,1993年9月27日结构封底,提前64天完成主体结构,同年10月底,该施工技术通过了专家鉴定。专家们认为:该技术在总体上达到了国际先进水平。常熟路车站如采用顺作法施工,其施工顺序见图1。逆作法施工顺序见图2。
Subway Changshu Road Station by the Fifth City Construction Engineering Company contractors, the use of the original reverse construction technology for construction. The project broke ground on February 10, 1992, and the structure back cover was completed on September 27, 1993. The main structure was completed 64 days in advance. By the end of October of the same year, the construction technology passed the expert appraisal. Experts think: The technology has reached the international advanced level as a whole. Changshu Road Station, such as the use of Shun approach construction, the construction sequence shown in Figure 1. The reverse construction sequence shown in Figure 2.