设计规模为日处理原矿 750t/d的阿希金矿 ,其各项经济技术指标堪称国内领先、国际先进水平。经过几年的生产 ,尾矿坝服务年限缩短 ,尾矿设施技改迫在眉睫。为优化设计 ,对尾矿压滤和尾矿坝加高两方案做了技术经济比较 ,并推荐采用尾矿压滤新工艺 ,付诸实施后 ,取得了显著的经济和社会效益 ,年净增产值 52 0多万元
The designed scale is Ashi Gold Mine, which has a daily processing capacity of 750t / d. The various economic and technical indexes are domestically advanced and internationally advanced. After several years of production, the service life of the tailings dam has been shortened, and the technological transformation of tailings facilities is imminent. In order to optimize the design, the technical and economic comparisons of tailings pressure filtration and tailings dam height enhancement were made, and the new technology of tailings pressure filtration was recommended. After implementation, significant economic and social benefits have been achieved, with a net annual increase The output value is more than 5 million yuan