论文部分内容阅读
转眼四十多年过去了,当年在抚顺石油二厂会战吊装我国第一套新型催化裂化装置的情景,特别是被誉为“钢铁起重队”队长的林斤亭吹着响哨、挥着小红旗指挥起吊的场景,还深深地留在了脑海中。那是1964年夏末秋初,石油二厂负责承建的我国第一套新型催化裂化装置建设正在节骨眼上,眼前的关键是要把两台预制好的上百吨重的反应器和再生器这两个庞然大物,赶紧从预制场运到装置现场。虽说只有1公里远,可在当时是个大难题。能拉
More than 40 years later, Fushun Petrochemical Plant 2 was the scene of the first new type of catalytic cracking unit to be hoisted in China. In particular, Lin Kuping, known as the captain of “Steel Lifting Team,” whistled and waved Small red flag command lifting scene, but also deeply stuck in my mind. That is the beginning of the summer of 1964, the construction of the first new type of catalytic cracking unit under the responsibility of China’s Second Oil Plant is at a critical juncture. The immediate point is to take two prefabricated reactors and regenerators weighing hundreds of tons Two monster, quickly transported from the prefabricated site to the installation site. Although only 1 km away, at that time was a big problem. Can pull